Railway construction

Infrastructure measures SBB Zugersee Ost, structural work

Walchwil ZG, Switzerland / 03.2019 - 09.2020

The 15km long railway line from Zug to Arth-Goldau was rehabilitated in four sub-projects. The existing double track in front of Walchwil station was extended by 1.7km. The work comprised a total of 128 objects. In addition, dismantling of the railway infrastructure and creation of eleven access roads to the track with six installation sites were necessary.

The four sub-projects were carried out on two construction sites. Construction site A ran over a length of 8.65km from Zug railway station to the Sagenbachbrücke. Construction site B extended over a distance of 6.35km from the Sagenbachbrücke to Arth railway station.

Photo: View of the double-track extension from afar along a slope surrounded by houses and landscape; at the foot of the hill of Lake Zug

Facts & Figures


Company

PORR SUISSE AG as part of a consortium

Type

Railway construction

Runtime

03.2019 - 09.2020

Principal
SBB AG

Double track extension with lake view.

The four sub-projects were:

1. double-track extension Walchwil

2. substance preservation single-track tunnel

3. substance preservation of buildings and roadway Zug - Arth-Goldau

4. protective structures (Baltisberg and Härzigwald)

After one and a half years of construction, the project was completed to the fullest satisfaction of the client SBB AG.

To the SRF report «Tight deadlines at SBB's longest construction site”

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.