Reuss bridge, Meitschligen

Gurtnellen, Switzerland / 04.2016 - 08.2018

The Reuss bridge in Meitschligen is part of the K2 Gotthardstrasse. In 2014, initial maintenance works were carried out on the span's superstructure. Two years later, PORR began the sealing process with a reinforced concrete slab reaching across both ends of the bridge. Works were completed in August 2018. The road surface of the heritage-listed natural stone arched bridge was completely rebuilt and widened slightly.

Photo: old, heritage-listed natural stone arched bridge seen from the side; ravine in front; mountain landscape and forest behind
© PORR

Facts & Figures


Company

PORR SUISSE AG

Type

Bridge construction

Runtime

04.2016 - 08.2018

Principal
Canton Uri, Office of Civil Engineering

Renovation with historical significance.

During the first construction stage, the PORR team finished the new road surface slab with a sealing layer of polybutadiene polymer-modified bitumen and poured asphalt. The next step involved the creation of a partially anchored supporting wall and the renewal of the road superstructure. The completion of the central road surface with rapid-setting concrete ensured that road traffic could remain uninterrupted during the day.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.

Photo: old, heritage-listed natural stone arched bridge seen from the side; ravine in front; mountain landscape and forest behind
© PORR
Photo: bridge road surface under construction; road with different surface layers divided by marker rods; two cranes; in background, a slope with forest and fields
© PORR
Photo: bridge with downhill supporting wall under construction; at the foot of the wall, a construction site with equipment and materials
© PORR